Sayfadaki görseller
PDF
ePub

b. 9 by 12 by 24 inches.

2. Web-14 to 3 inches.

I. VARIABLES IN THE MANUFACTURE OF BLOCKS UNDER INVESTIGATION-continued.

C. Dimensions of specimen:

1. Outside.

a. 8 by 8 by 16 inches.

F. Process of manufacture—Continued. 2. Molding-Continued.

b. Damp and medium mixtures-cast in molds from which speci

mens are removed before hard set.

(1) Hand tamped.

(2) Power tamped.

(a) Air.

(b) Mechanical.

x. Single application.
y. Repeated applica-
tion.

3. Air space-30 to 333 per cent.

D. Consistency:

1. Damp.

2. Medium.

3. Wet.

E. Proportions:

1. Mortar.

a. 1:2.

b. 1:4.

c. 1:8

d. Balanced proportions for water

proofing.

2. Concrete.

a. 1:2:4.

b. 1:2:5.

c. 1:3:6.

d. Balanced proportions for water

proofing.

F. Process of manufacture:

1. Mixing.

a. Hand.

b. Machine.

2. Molding.

a. Wet mixture-cast in molds in which test pieces remain

until hard set.

(1) Sand molds.

(a) Poured without vibration.

(b) Poured with vibration.

(2) Metal molds.

G. Curing:

1. Natural.

a. Air.

b. Air and sprinkling.

2. Artificial.

a. Submerging.

b. Steam.

(1) Low pressure. (a) With CO2. (b) Without CO2. (2) High pressure. (a) With CO2. (b) Without CO2.

H. Aging:

1. Blocks that are fired.

2. Blocks that are not fired.

a. 4 weeks.

b. 13 weeks.

c. 26 weeks.

d. 52 weeks.

J. Use of waterproofing compounds: 1. Applied to surface.

[blocks in formation]
[blocks in formation]

Method. The mixing is performed in the same manner as described under "Beam section" (pp. 48-50). The mortar entering the blocks that have been made has been so dry that the forms could be removed as soon as the tamping was completed. Two men are employed in molding the blocks-one to shovel the material into the molds and one to tamp. The concrete is put in the molds in 3-inch layers and tamped with a hand or pneumatic tamper, care being taken to tamp all the blocks in the same manner and the same length of time.

As soon as the tamping is finished, the sides of the forms are removed and the block is weighed and placed in the moist storage room. The weight of the blocks in any one batch is not permitted to vary more than 1 per cent. After the sides of the molds are removed the blocks are allowed to remain on the bottom for sixty

hours. At the end of this time they are marked and piled in the order in which they are to be tested.

Apparatus. All the mortar and concrete used in the tests are mixed in a one-half cubic yard Chicago cube mixer, which is mounted on skids and is motor driven. The discharging end of the mixer appears in the background at the left in Pl. XX, which shows the mixing and molding room. Through the open doorway near the center of the picture can be seen the testing room. The water used is weighed in the barrel resting on the platform scales, the process being similar to that described under "Constituent-materials section" (p. 32).

STORAGE.

One of the moist rooms for the storage of blocks and cylinders is shown in Pl. XIX, B. There are two of these rooms, which are lined with moisture-proof paper and furnished with water and steam sprinklers near the ceiling. The specimens are sprinkled at regular intervals of eight hours. The five different types of blocks and corresponding cylinders may be seen in Pl. XIX, B.

STRENGTH TESTS.

Apparatus. The strength tests of the blocks and corresponding cylinders are made on a 200,000-pound 4-screw motor-driven testing machine, a portion of which will be seen through the doorway in Pl. XX.

The blocks are first tested for transverse strength on a span of 20 inches, the load being applied at the center of the span. Pl. XXI, A, shows a building block in the testing machine ready for application of the load. An isometric drawing of each block is given to the operator and the position of the break is sketched upon the drawing, the distance of the break from one end of the block being measured and recorded on the drawing.

The two pieces of the block resulting from the transverse test are placed in the testing machine one at a time and tested for compressive strength. A half block ready for testing is shown in place in the testing machine in Pl. XXI, B. The top and bottom of the block are bedded with thick sheets of asbestos, and the spherical bearing block (a) assures an even distribution of the load.

Before these halves are tested, the top and bottom surfaces of each are traced, full size, on large sheets of paper for the purpose of getting the least area subjected to compressive stress. The load at the first crack and the breaking load are recorded.

The ends of the cylinders are smoothed off with plaster of Paris and are tested as described under "Constituent-materials section" (pp.

[graphic][merged small][subsumed][subsumed][merged small][ocr errors]

A. BUILDING BLOCK IN MACHINE READY FOR TRANSVERSE TEST.

B. ONE-HALF OF BUILDING BLOCK IN MACHINE READY FOR COMPRESSION TEST.

[graphic]

1

« ÖncekiDevam »